BATON ROUGE, Louisiana — Today, weeks after a national election revealed a country fed up with high prices and data centers, Louisiana residents and organizations rallied in downtown Baton Rouge against gas plants for a massive Meta data center. Marching and rallying with signs and megaphones, the group urged the Louisiana Public Service Commission (PSC) to reject Entergy’s proposal to build seven expensive, polluting gas plants for Meta’s Hyperion campus.

Entergy wants PSC approval to build seven additional gas plants for the Meta data center, which will need more energy than a city four times as large as New Orleans. The utility doesn’t want to implement the common-sense customer protections requested by numerous groups intervening in the case. Sierra Club has been urging rejection of this proposal for months because it presents a “substantial cost” that Entergy’s existing customers may be required to bear.

According to recent reports, due to Gov. Jeff Landry’s “lighting speed” initiative and a previous decision by a majority of PSC commissioners, the agency is rushing this proposal through and planning to provide only one opportunity for the public to speak out against this proposal: a December meeting when commissioners are scheduled to also vote on the proposal minutes later. Much of the analysis Entergy has submitted to the PSC has been shielded from public view by NDA restrictions.

In response to the PSC’s upcoming decision, Louisiana residents and Sierra Club staff, issued the following statements:.

Industry observers note that “It’s clear by now that Meta and Entergy don’t care much for normal Louisianans, but the PSC has a mandate to do just that. Instead they have denied  us a meaningful opportunity to speak on a project that will impact our state for generations,” mentioned Margie Vicknair-Pray, project coordinator for the Sierra Club and a Louisiana resident. “Commissioners must know that the people will not sacrifice Louisiana for one massive, risky, expensive, polluting experiment. They must vote no on this outrageous corporate favor.”.

According to recent reports, “Any claims that Meta is fully paying its own way are false,” mentioned Darryl Malek-Wiley, a senior field representative for Sierra Club and a Louisiana resident. “These seven gas plants will guzzle our water, pollute our air, – and customers will be on the hook to pay if Meta walks away. We’re here to tell commissioners that we are done footing the bill for big tech – especially considering the extreme lack of transparency surrounding this project.”.

In its testimony to the PSC urging rejection of Entergy’s proposal, Sierra Club called for:.

In negotiations, Entergy showed little willingness to consider or agree to any of these stipulations.

In a recent development, separately, in Meta’s application to the LDEQ, it wants to modify its existing permit to add 44 fossil-fuel water boilers that will operate and emit pollutants around the clock. Because this would send total pollution for the permit beyond the minor-source permit limits, Meta said that – instead of applying for a major source permit as required by the Clean Air Act – it simply wouldn’t count emissions from the previously approved 31 diesel generators when those are operating during emergency hours.

Sierra Club has urged LDEQ that it must consider emissions from those diesel generators running during emergency operations.