Theta Gold Mines (ASX: TGM) is targeting its first gold pour in the March quarter of 2027 as construction of its Transvaal Gold Mining Estates (TGME) project in South Africa approaches completion.
Executive chair Bill Guy outlined progress at the annual general meeting in Sydney on 27 November, with construction of the gold processing plant 81% complete and development expenditure estimated at A$84.8 million (US$56m) to the end of October.
The company has completed two drawdowns under its Nordic bond financing and has stockpiled 110,000 tonnes of ore in preparation for plant commissioning.
Theta Gold holds a 74% interest in the project in Mpumalanga province, where its revised feasibility study completed in February outlined a 13.1-year operating life.
The A$136.4m (US$90m) senior secured bond matter Theta completed in June provides funding for project development over a four-year term at an annual coupon rate of 12.75%, with interest payable quarterly in advance.
Theta completed the second drawdown on 25 November, taking total proceeds released under the facility to A$109.6m (US$72.6m), with further releases dependent on construction funding requirements and cost-to-complete tests.
The company reported an existing cash balance of approximately A$96.2m (US$63.52m) at 25 November, with an undrawn bond balance of A$20.8m (US$13.7m).
The remaining facility includes a provision for cost overruns subject to approval by independent technical engineer Behre Dolbear Australia, which monitors the project build.