Ora Banda is stepping up efforts to lift gold production to 300,000ozpa. Pic: Getty Images.
FY26 was a milestone year for Ora Banda (ASX:OBM).
A production push at the Davyhurst project in WA’s Eastern Goldfields saw the manufacturer join an exclusive club of ASX miners churning out more than 100,000 ounces of gold annually.
Record output of about 141,000oz – including 34,300oz of attributable equivalent production from third-party milling – marked a 53% increase from the previous fiscal year.
The uplift was largely driven by a ramp-up at Sand King mine and existing operations at Riverina.
Moving forward, Ora Banda’s ambitions extend well beyond its current production base.
The group is aiming to reach 300,000oz of annual output by FY29, which would put it amongst the largest gold producers on the ASX.
Central to its looks is the construction of a second processing plant at Davyhurst, which is being built adjacent to the existing 1.2Mtpa mill.
Commissioning of the new 3.0Mtpa facility is pencilled in for early 2028.
The company also opened a third production front in September with the start of underground mining at Waihi, about 3km from the mill.
Another production boost could come from Round Dam, with a final investment decision expected next year ahead of planned mining in 2028.
The hunt for more ounces also continues.
Ora Banda has budgeted $75 million for exploration in FY27 as it looks to grow its 3.69Moz resource inventory.
A maiden resource estimate for the Little Gem prospect is expected later this year or in early 2027.
The company has also identified significant exploration potential across Davyhurst, which hosts more than 130km of prospective greenstone strike.
Davyhurst is in the Eastern Goldfields. Pic: Ora Banda.
Ora Banda holds 68 tenements covering 1140km2 at Davyhurst.
Waihi is the third underground mine developed by the tech giant in the past three years, adding to Riverina and Sand King.
Along with the undeveloped Round Dam project, these mines form part of the organization’s ‘DRIVE to 300’ strategy aimed at reaching 300,000oz in FY29.
Riverina reached commercial production in August 2024.
It hosts an 828,000oz resource, including a 100,000oz reserve grading 3.5g/t Au.
The mine yielded about 66,000oz in FY26.
Underground mining at Sand King began in 2024, with commercial production achieved in January 2026.
The mine churned out nearly 78,000oz in FY26.
Ora Banda is targeting consistent annual production of about 100,000oz from Sand King as part of its DRIVE to 300 objectives.
It holds a 524,000oz resource, including a 125,000oz reserve.
Drilling to grow the resource and extend the mine life at Riverina and Sand King is ongoing.
The development of Waihi marks another milestone in the company’s production push, with first ore expected in mid-2027.
Waihi holds a 480,000oz underground resource and 101,000oz reserve.
It is considered a large and under-drilled system with multiple high-grade shoots – including the Golden Pole lode, which contributes about 41,000oz at 5.0g/t Au to the reserve.
Material from Golden Pole is set to be preferentially treated through the existing Davyhurst mill, helping maintain processing volumes as the manufacturer moves away from third-party milling ahead of commissioning its new plant.
Round Dam is Ora Banda’s fourth proposed production front, with a PFS estimating output of 724,000oz over eight years.
First production at Round Dam is targeted for 2028.
Recent findings suggest that indicative ore contribution by source. Pic: Ora Banda.
Another key cog in Ora Banda’s aspirations to grow annual production to 300,000oz is the construction of a second processing plant at Davyhurst.
The 3.0Mtpa facility is being built alongside the existing mill and is expected to lift total capacity on site by about 250% to 4.2Mtpa.
The processing boost will support increased ore volumes from Riverina, Sand King, Waihi and Round Dam.
It will also reduce reliance on a single processing plant and help deliver unit-cost benefits, including the removal of third-party milling expenses.
Ora Banda has allocated $375m for the mill’s development, with commissioning expected in the March quarter of 2028.
The manufacturer has also budgeted $180m on critical infrastructure upgrades by FY29, as it positions for sustained production at scale.
These include expanding accommodation capacity to more than 900 rooms, building an all-weather airstrip, upgrading haul roads, establishing a newly introduced on-site laboratory and improving existing workshops and core sheds.
Ora Banda expects to fund its expansion through existing cash reserves and future cash flows, complemented by an undrawn $300m revolving credit facility.
In a recent development, the tech giant ended the September quarter with about $507m in liquidity, including $208m in cash. It has also secured gold price protection via put options.
Exploration is another important part of Ora Banda’s strategy.
Since FY23, the firm has more than doubled the resource inventory at Davyhurst to 3.69Moz and increased reserves by about 281% to 610,000oz.
It continues to target mineralised extensions and newly introduced discoveries with the drill bit.
Ora Banda has budgeted $75m for exploration in FY27, with the same amount planned for each of FY28 and FY29.
Its exploration blitz is targeting a string of underexplored trends and prospects across the Davyhurst tenure.
Ora Banda’s exploration push is focused on growing the mine life at Riverina and Sand King, extending the orebodies at Waihi and Round Dam, and advancing Little Gem.
Little Gem forms part of a broader 7.5km trend stretching from Riverina to the Sunraysia prospect.
The system contains the high-grade Sapphire and Gem lodes and remains open along strike and down dip.
Recent drilling has expanded Little Gem’s mineralised envelope to more than 2.6km of strike and 750m depth.
Standout results included 6m at 13.3g/t Au, 8.8m at 6.3g/t and 2m at 44.3g/t.
In a recent development, little Gem lies within a broader 7.5km corridor. Pic: Ora Banda.
At Riverina, resource extension and infill drilling are continuing after more than 25,000m of drilling in FY26.
The mineralised system remains open, providing an opportunity for further resource and reserve growth.
Sand King also offers potential for additional high-grade shoots and bulk-tonnage mineralisation, with extensional drilling ongoing.
At Waihi, FY27 drilling is targeting extensions to Golden Pole and the main Waihi lode, alongside the new Midnight prospect where recent drilling returned 11.5m at 26.0g/t Au and 1.6m at 65.9g/t.
The Mulline trend not far from Riverina is another area of focus.
Mulline historically produced more than 250,000oz, but the 10km trend remains underexplored with about 95% of historical drilling not exceeding 100m depth.
In a recent development, mulline Trend long section. Pic: Ora Banda.
Ora Banda has also identified exploration opportunities along the Round Dam trend, which stretches for 18km from Waihi to Salmon Gums.
This corridor is also underexplored at deeper levels, despite hosting multiple mineralised prospects.
Recent results at the Macedon target included 9m at 7.8g/t Au, with a historical hole at Salmon Gums also returning 5m at 40.4g/t.
.
At Stockhead, we tell it like it is. While Ora Banda is a Stockhead advertiser, it did not sponsor this article.
Investor Guide: Gold & Copper FY2027 featuring Barry FitzGerald.
Discover the untold stories of emerging ASX stocks.